Permitted Use Review – Uses identified in Augusta Land Use Ordinance as ‘permitted’ uses within a given zone.
Review & Approval Authority | Code Enforcement Bureau |
Required Submittal | Application |
Review Time Frame | 10 working days |
Other requirements, including fees | Performance guarantee must be posted for cost of improvements in public right of way. Application fees vary. |
Conditional Use Review – Uses identified in Augusta Land Use Ordinance as ‘conditional’ uses within a given zone.
Review & Approval Authority | Planning Board |
Required Submittal | Application |
Review Time Frame | One public hearing must be held. Planning Board usually meets twice per month. |
Other requirements, including fees | $50.00 application fee is required. |
Major and Minor Development Review – Developments as defined in the Augusta Land Use Ordinance.
Review & Approval Authority | Planning Board |
Required Submittal | Application |
Review Time Frame | For a minor development, one public hearing must be held. For a major development, two public hearings must be held that are at least 30 days apart. Planning Board usually meet twice per month. |
Other requirements, including fees | Application fees vary. |
Major and Minor Subdivision Review - Subdivisions as defined in the Augusta Land Use Ordinance.
Review & Approval Authority | Planning Board |
Required Submittal | Application |
Review Time Frame | For a minor subdivision, one public hearing must be held. For a major subdivision, two public hearings must be held that are at least 30 days apart. Planning Board usually meet twice per month. |
Other requirements, including fees | Performance guarantee must be provided for new roads. Application fees vary. |